Jun 2 2009

Frame nearing completion

As the frame is nearing completion I am turning my attention to the roof. I have already ordered the tiles from Tudor Roof Tiles and am awaiting a delivery date. We have chosen a mixture of 2 colours, 65% medium antique and the remainder the plain red as with our other buildings on the site. [...]

May 7 2009

Oak frame is coming together

The welsh oak guys were back on site just before midday Tuesday following the bank holiday break as they had not booked the crane till Wednesday they spent the rest of the day fixing the panels they could lift by hand but even so things started to take shape. Buy the end of the day [...]

Apr 20 2009

Oak Frame Delayed

Welsh Oak have been delayed by the weather on another site and have had to pospone the delivery and erection of our frame. It is really dissapointing as this is the second delay and we will now be 5 weeks behind schedule assuming they do turn up next monday. With the cacellation of the frame [...]

Mar 29 2009

Received our bricks approval

Yesterday we finally received the brick, roof tile and driveway materials approval from the council so first thing on Monday morning I will get in contact with my Tudor Roof Tile rep and finalise the tiles. Although I have been dealing with the Hogkins Bricks rep regarding quantities and specials brick they will only take [...]