Apr 29 2009

The Oak frame has started to go up

The crane arrived first thing as arranged, as the ground is pretty soft it took quite a while to get set as we needed matts ouspread the weight out. Ang brought the kids up on the way to school to see the crane, they seemed really exited and could not wait to go and tell [...]

Apr 28 2009

Oak frame is a jigsaw

The guys from Welsh Oak Frame spent the morning covering the brickwork below the damp with polythene to protect it from staining by the tannin in the wood, they then fixed the sole plate on the damp proof coarse to stand the Oak frame on. After a decent sunny morning the rain has returned but [...]

Apr 27 2009

Oak Frame is here!!

This morning I was up and about early despite a bit of a family get together yesterday as we were having a forklift delivered to the site to unload the Oak frame. As we had been let down on a couple of occasions on the frame delivery I was relieved to get a call from [...]

Apr 20 2009

Oak Frame Delayed

Welsh Oak have been delayed by the weather on another site and have had to pospone the delivery and erection of our frame. It is really dissapointing as this is the second delay and we will now be 5 weeks behind schedule assuming they do turn up next monday. With the cacellation of the frame [...]