Mar 29 2009

Received our bricks approval

Yesterday we finally received the brick, roof tile and driveway materials approval from the council so first thing on Monday morning I will get in contact with my Tudor Roof Tile rep and finalise the tiles. Although I have been dealing with the Hogkins Bricks rep regarding quantities and specials brick they will only take [...]

Mar 14 2009

Block work upto slab

We are upto slab level with the block work,  the ground was not as level as I had first thought which will give us about 6 course’s of face work on one corner which is not to much of a drama. Once the slab has been laid we will have another coarse of block work [...]