Apr 20 2009

Oak Frame Delayed

Welsh Oak have been delayed by the weather on another site and have had to pospone the delivery and erection of our frame.

It is really dissapointing as this is the second delay and we will now be 5 weeks behind schedule assuming they do turn up next monday.

With the cacellation of the frame delivery we did not have to rush to get the scaffolding up and finished over the weekend so that is being completed over the next couple of days.

In the meantime I am getting a rep from keymer roof tiles in this afternoon as I really need to make a decision on the tiles and get them ordered.