Apr 6 2009

New build latest

I have ordered the first lorry load of bricks and I am hoping they will be delivered on Wednesday, I say hoping as I have provisionally got the bricklayers coming back to me on Friday and Saturday to finish up to the DPC.

All being well I will then be able to get the scaffolders in next week as the scaffold will need to be complete for the Oak Frame to be delivered on Monday the 20th! I cant wait, I am hopeful the Self Build Webcam will be up and running by then as I am sure that the actual frame build will be the most interesting part of the whole build.

I have also been in contact withVale regarding the bronze casements and the joiners about the frames as the prices are still very high and I am doing my best to get them down a bit.

The heating is also proving to be more expensive than I hoped to pay, I thought I had decided on a ground source heat pump but the cost seems excessive and I just can not see how the figures pay back figures can be correct.

Once Welsh Oak are here I will spend a bit more time on resolving the heating and the windows.