Bricklayers have completed the chimney’s
Both chimneys are now up just need to get the roofers to dress the lead once they have got the roof tiles on.
Installing Insulation Over The Exposed Oak
This week we have started started installing the Celotex insulation over the exposed Oak. This involves laying 12.5 mm foil backed plaster board directly on top of the Oak then a layer of 80 mm Celotex, roofing batten is then laid in the same direction as the Oak rafters and fixed in place with 150 [...]
Roof glazing bars installed today
Today we have had the Glazers in to fit the roof bars for the roof window that will allow has views of the gardens from the gallery landing, it will also make our sitting room very light and airy. There was a lot of discussion as to why Welsh Oak Frame have designed the Oak [...]
Manic Tuesday
Today has been manic. I have started a labourer on site as I just cannot keep up with the “little jobs” that I have been trying to do but that seem to end up taking up most of the day and just never seem to get finished so the sensible thing to do was take [...]

