Mar 25 2009

Welsh Oak visited the site

Met up with our Welsh Oak Frames project manager Keith at lunchtime, he needed to take a look at the site in preparation for the oak frame delivery. He also wanted to check our groundwork measurements for accuracy and  run through the scaffolding drawing’s that Welsh Oak had already provided showing where they required scaffolding [...]

Mar 14 2009

Block work upto slab

We are upto slab level with the block work,  the ground was not as level as I had first thought which will give us about 6 course’s of face work on one corner which is not to much of a drama. Once the slab has been laid we will have another coarse of block work [...]

Mar 3 2009

Where we are now

We have not had anyone on site the last few days however bricklayers are due to start later this week . I ordered blocks, sand and cement last week and took delivery today – just hope they turn up! I have a chap from  Architectural Bronze Casements coming to see us on Friday, I have [...]

Page 5 of 5« First...2345
eXTReMe Tracker
Blog Directory

Blogroll