Jun 26 2009

Open Eaves

Having chosen some exposed rafters in the Master bedroom and in the sitting room at the design stage we decided to have conventional ceilings in the other bedrooms. We did this for to go this route mainly because of the extra cost having Oak rafters throughout.
Once Welsh Oak left the first thing I did was [...]

Jun 2 2009

Frame nearing completion

As the frame is nearing completion I am turning my attention to the roof.
I have already ordered the tiles from Tudor Roof Tiles and am awaiting a delivery date. We have chosen a mixture of 2 colours, 65% medium antique and the remainder the plain red as with our other buildings on the site.
I also [...]

Apr 29 2009

The Oak frame has started to go up

The crane arrived first thing as arranged, as the ground is pretty soft it took quite a while to get set as we needed matts ouspread the weight out. Ang brought the kids up on the way to school to see the crane, they seemed really exited and could not wait to go and tell [...]

Apr 20 2009

Oak Frame Delayed

Welsh Oak have been delayed by the weather on another site and have had to pospone the delivery and erection of our frame.
It is really dissapointing as this is the second delay and we will now be 5 weeks behind schedule assuming they do turn up next monday.
With the cacellation of the frame delivery we [...]