May 13 2009

Ground floor Oak mostly completed

A little over 2 weeks of the Oak frame being on site and we now have the bare carcus of the ground floor completed. Earlier today we had the remainder of the roof trusses delivered, so we know have everything on site to complete the frame. So tomorrow they will start on the first floor [...]

May 7 2009

Oak frame is coming together

The welsh oak guys were back on site just before midday Tuesday following the bank holiday break as they had not booked the crane till Wednesday they spent the rest of the day fixing the panels they could lift by hand but even so things started to take shape. Buy the end of the day [...]

May 1 2009

Bank holiday weekend

Bank holiday weekend and it looks like being a scorcher, the Welsh Oak guys cam in for a few hours but then headed back to Wales for the weekend so we will not see them till mid morning on Tuesday now. I wont know what to do with myself as I have spent most of [...]

Apr 29 2009

The Oak frame has started to go up

The crane arrived first thing as arranged, as the ground is pretty soft it took quite a while to get set as we needed matts ouspread the weight out. Ang brought the kids up on the way to school to see the crane, they seemed really exited and could not wait to go and tell [...]