Sep 7 2009
Window have arrived
Over the weekend we had the Oak window frames delivered to the site, this morning the Bob and Nick arrived to install them.
Sep 6 2009
Bricklayers have completed the chimney’s
Both chimneys are now up just need to get the roofers to dress the lead once they have got the roof tiles on.
Sep 1 2009
Installing Insulation Over The Exposed Oak
This week we have started started installing the Celotex insulation over the exposed Oak. This involves laying 12.5 mm foil backed plaster board directly on top of the Oak then a layer of 80 mm Celotex, roofing batten is then laid in the same direction as the Oak rafters and fixed in place with 150 [...]
Aug 29 2009
Oak Window Frames
Our Oak window frames are now nearly ready for delivery so I went down to Bobs workshops to take a look. Things seem to be moving in the right direction again.