May 26 2009

Oak in the final stages

Back from the bank holiday break the Oak Frame is in the final stages of completion, there is one gable end and a stack of rafters to be lifted into place and then most of the first floor frame joints will need to be pinned. I have contacted www.oakcleaning.co.uk to get some idea of the [...]

TAGS:
May 19 2009

First floor Oak is going up

The lads from Welsh Oak are now putting up the Oak to form first floor which has Oak exposed both externally and internally as opposed to the ground floor which has a brick facad with the only exposed on the inside. As part of the concession we agreed with the planning department to get planning  [...]

May 13 2009

Ground floor Oak mostly completed

A little over 2 weeks of the Oak frame being on site and we now have the bare carcus of the ground floor completed. Earlier today we had the remainder of the roof trusses delivered, so we know have everything on site to complete the frame. So tomorrow they will start on the first floor [...]

May 7 2009

Oak frame is coming together

The welsh oak guys were back on site just before midday Tuesday following the bank holiday break as they had not booked the crane till Wednesday they spent the rest of the day fixing the panels they could lift by hand but even so things started to take shape. Buy the end of the day [...]